Building Blog - 5/5/26

Published May 5, 2026
Building Blog - 5/5/26

Building
Heavy, persistent rains over the past few weeks have slowed progress, but work is moving forward again. Retaining walls are currently being formed, with half scheduled to be poured this week and the rest next week. The main floor slab is expected to be poured in the next 2–3 weeks. Once that’s complete, progress will become much more visible as construction begins to rise above ground.

Park
Out at the park, the fishing dock is nearing completion and the walking paths are close behind. The well-house for the irrigation pumps will be erected soon, and hydroseeding is scheduled for next week. Thank you for your prayers and support as we continue making room for more!